Plan is to have all the holes dug and filled in with gravel, cinder block and a little bit of cement to help keep it level
Too start off we had to mark out from the center pole and mark where the center of the bench will go, then we would have to go out 3 feet from the center point to mark one edge of the pillars, we then did an outline of the pillars so we have a rough idea of how big the hole had to be.
After the first bench was dug out we used it as a guide to see how deep we had to go.
After we started one hole we had to mark out the second bench. After the second bench was marked out we had to mark out the third. There were two scouts per a bench to dig and it turned into a friendly competition for the scouts against the adults
This is the first complete base done and leveled that we are using as a guide to go off of.